| The way to the beach Long beach promenades in historical bathing locations, wicker beach chairs standing to the left and right bring city life directly down to the seaside. The bathing world set in the Art Nouveau period is finding a new lease of life. "The Way to the Beach" is reminiscent of holidays, seaside and holiday fun. The new public baths are to make holidays on your own doorstop more possible than ever before. |
| Key Figures and Facts Start of Construction _ December 2004 (Phase I) Completion _ May 2006 (Phase II) Construction Costs _ 3.2 Mio. EUR* Project Manager _ Christoph Rahrbach *excluding VAT, CG 200-600 Building Volume _ 1,214 m³ (Beach Bar) Useable Area Monument _ 2,105 m² Covered Area _ 306 m² (Beach Bar) |